Standard bagged or ready-mix concrete is hard enough to walk on after about 24 hours, but it takes 28 days to reach its full design strength. Most mixes can take a car after 3 days and heavier vehicles after 7. Keep the slab moist for the first 5 to 7 days: “drying” and “curing” aren’t the same thing, and concrete that dries out too early ends up weaker.
Open the concrete calculator Enter your slab size and thickness to get cubic yards and bags.

New concrete timeline: what you can do, and when
These times are for a standard concrete mix in mild weather (above 50°F), counted from when the concrete is placed. Each one comes from the product sheet or standard named next to it. Cold weather, a wetter mix or a thicker pour all push them later.
| Time after pouring | What it means | Source |
|---|---|---|
| About 6 hours | Initial set: the surface is hard to the touch | Sakrete Concrete Mix data sheet (Canada) |
| 24 hours | Light foot traffic; a set post can take strain | Sakrete High-Strength; Quikrete Concrete Mix |
| 48 hours | End of the minimum frost-protection window | Quikrete and Sakrete both say protect from freezing for 48 hours |
| 3 days (72 hours) | Cars and light vehicles | Sakrete High-Strength; ACI 330R (via FHWA), above 16°C / 61°F |
| 5–7 days | Keep the surface moist this long | Quikrete: 5 days at 70°F or warmer, 7 days at 50–70°F |
| 7 days | Heavier vehicles; about 2,500 psi | ACI 330R (via FHWA); Quikrete Concrete Mix data sheet |
| 28 days | Design strength, about 4,000 psi | Quikrete Concrete Mix data sheet; Sakrete High-Strength |
Fast-setting and high-early-strength products run on a much shorter clock. Go by the bag, not this table, if that’s what you poured.
Drying, setting and curing aren’t the same thing
People say “dry” but what they usually mean is “set” or “cured”.
- Setting is the change from a workable paste to a solid. Sakrete says its Concrete Mix sets in about 6 hours, and once a slab has set you can no longer finish it.
- Curing is keeping the concrete moist and warm enough so the cement keeps reacting with water (hydration) and gains strength. The American Concrete Institute describes it as maintaining moisture and temperature so the mix can develop its properties, and says the reactions need internal relative humidity over 80% and temperatures above 50°F (10°C).
- Drying is water leaving the slab. It goes on for weeks, and drying out too early is exactly what curing tries to prevent.
So a slab can look dry and pale on day two and still be nowhere near its final strength. And a slab that dries out in the first few days doesn’t catch up later. NRMCA’s Concrete in Practice sheet on curing says concrete left in a dry environment can lose as much as 50 percent of its potential strength compared with concrete that’s moist cured.
How long to keep concrete moist
The published guidance lands in the same range, 3 to 7 days:
- Quikrete’s Concrete Mix data sheet: start curing as soon as possible and keep going for 5 days in warm weather (70°F or higher) or 7 days at 50°F to 70°F.
- Sakrete’s High-Strength Concrete Mix data sheet: keep it continuously moist for 3–5 days after it sets and keep it from freezing for 48 hours.
- NRMCA (CIP 11): curing typically runs 3 to 7 days, and the concrete should be kept above 50°F.
- The ACI 308.1 curing specification’s default is at least 7 days, as summarized in the FHWA guide to curing concrete pavements. That guide also notes that ACI allows curing to stop early once the concrete reaches 70 percent of its specified strength.
If you’re not sure, plan on 7 days. It costs nothing but a little patience and a garden hose.
How to keep it moist
Pick one method and stick with it:
- Curing compound. Spray or roll on a cure-and-seal once the surface is hard, so it can’t evaporate water. Quikrete says not to apply it if rain or temperatures below 50°F are expected within 24 hours.
- Plastic sheeting. Lay it flat once the concrete is hard enough not to mark, and weight or tape the edges. NRMCA says it should overlap the slab edge by at least twice the slab thickness. Wrinkles can leave dark streaks, so skip plastic on colored or decorative concrete.
- Wet burlap or a sprinkler. Keep it wet the whole time. Letting it dry out in the afternoon and wetting it again at night defeats the point.
When can you walk and drive on new concrete?
Walking
Sakrete says its High-Strength Concrete Mix opens to foot traffic in 24 hours, and the Concrete Network curing guide gives 24 to 48 hours. Keep it to careful walking at first. Dragging furniture, wheelbarrows or a grill across it can scuff the surface.
Driving
Sakrete lists vehicle traffic at 72 hours. The FHWA guide summarizes ACI 330R (concrete parking lots) as no less than 3 days for cars and 7 days for all other traffic when it’s above 16°C (61°F), with more time when it’s cooler. Concrete Network says 7 days for light vehicles. For a new driveway, waiting the full 7 days before parking on it every day is the safer choice, and keep trucks, RVs and delivery vehicles off until then too.
Full strength
Quikrete’s data sheet lists its Concrete Mix at 2,500 psi at 7 days and 4,000 psi at 28 days. That puts it at about 62.5% of its 28-day strength after one week. Strength keeps climbing slowly after 28 days, but 28 days is the age the design strength is measured at.
What slows curing down
- Cold. Concrete Network says hydration slows down a lot below about 50°F and virtually stops below about 40°F. Fresh concrete must not freeze: NRMCA says to protect it until it reaches at least 500 psi, and Quikrete says to use plastic and insulation blankets for the first 48 hours if temperatures may drop below 32°F.
- Heat, sun and wind. Quikrete warns that hot, dry or windy weather pulls water out by evaporation, which can cause finishing problems and shrinkage cracking. NRMCA also notes that a high early curing temperature gives faster early strength but lower ultimate strength.
- Extra water in the mix. A soupy mix is easier to place, but Sakrete’s data sheet says plainly: do not overwater. Quikrete gives about 6 to 9 pints of water per 80 lb bag.
- The mix itself. Fast-setting and high-early-strength products are built to open sooner. Always check the bag or ask your ready-mix supplier.
Worked example: a 10×10 patio poured on a Saturday
Say you pour a 10×10 ft patio slab, 4 in thick, on a Saturday morning in late spring, with highs around 65°F.
- Concrete needed: 10 × 10 × (4 ÷ 12) = 33.3 cu ft, or 1.23 cu yd. With 10% extra that’s 62 bags of 80 lb mix or a 1.5 cu yd ready-mix order.
- Saturday afternoon: once the surface sets, cover it with plastic or apply a curing compound.
- Sunday morning (24 hours): you can walk on it carefully.
- Tuesday morning (3 days): a car could go on it per Sakrete and ACI 330R, but this is a patio, so there’s no reason to.
- Following Saturday (7 days): at 50–70°F Quikrete says to cure for 7 days, so the plastic comes off now. Patio furniture can go back.
- Four weeks later (28 days): the slab is at its design strength. Wait until then before sealing or staining if the product label asks for fully cured concrete.
Planning the pour: how much concrete for common slabs
Once you know the slab size work out bags or yards. The figures below come from the same math as the concrete calculator: 4 in thick, 10% extra, an 80 lb bag yielding 0.60 cu ft and a 60 lb bag 0.45 cu ft. Ready-mix is rounded up to the next quarter yard.
| Slab size | Volume | With 10% extra | 80 lb bags | 60 lb bags | Ready-mix order |
|---|---|---|---|---|---|
| 4×4 ft | 0.20 cu yd | 0.22 cu yd | 10 bags | 14 bags | 0.25 cu yd |
| 8×8 ft | 0.79 cu yd | 0.87 cu yd | 40 bags | 53 bags | 1 cu yd |
| 10×10 ft | 1.23 cu yd | 1.36 cu yd | 62 bags | 82 bags | 1.5 cu yd |
| 10×12 ft | 1.48 cu yd | 1.63 cu yd | 74 bags | 98 bags | 1.75 cu yd |
| 12×12 ft | 1.78 cu yd | 1.96 cu yd | 88 bags | 118 bags | 2 cu yd |
Past about one cubic yard, mixing bags by hand gets hard to finish in one go. That’s usually the point where people price a ready-mix truck.
Open the concrete calculator Enter your slab size and thickness to get cubic yards and bags.
This is general guidance for small DIY slabs, not engineering advice. For structural work, follow your local code and the instructions for the mix you use.
FAQ
How long does concrete take to dry?
It’s firm enough to walk on in about 24 hours, but it isn’t finished. Standard concrete reaches its design strength at 28 days, and the surface should be kept moist for the first 5 to 7 days so it cures properly instead of just drying out.
How long before you can walk on concrete?
About 24 hours for a standard mix. Sakrete’s High-Strength Concrete Mix opens to foot traffic at 24 hours, and Concrete Network gives 24 to 48 hours. Go easy for the first few days and don’t drag heavy things across it.
How long before you can drive on new concrete?
At least 3 days for a car and 7 days for heavier vehicles. Sakrete lists vehicle traffic at 72 hours, and ACI 330R (as summarized by FHWA) says no less than 3 days for cars and 7 days for other traffic above 61°F, longer when it’s cooler.
Should I water new concrete?
Keeping it moist helps, as long as you keep it moist the whole time. Quikrete says a lawn sprinkler is acceptable for curing but it must run continuously. Plastic sheeting or a curing compound does the same job with less babysitting.
Does concrete cure faster in hot weather?
It gains strength faster early on, but NRMCA notes that a high early curing temperature leads to lower ultimate strength. Heat and wind also dry the surface quickly, so curing matters even more in summer.
Can concrete cure in cold weather?
Slowly. Hydration slows a lot below about 50°F, and fresh concrete must not freeze. Quikrete and Sakrete both say to protect it from freezing for 48 hours, and Quikrete suggests plastic sheeting and insulation blankets if temperatures may drop below 32°F.
Figures are estimates for planning. Coverage varies by product and surface, so check the label before you buy.